Location – Grays Landing, Pennsylvania
The construction of a new lock and dam facility on the Monongahela River required the installation of a 2,000 ft. long temporary cellular cofferdam. The project schedule dictated this portion of the work be completed in four months. Richard Goettle, Inc. accomplished this work two shifts, six days per week.
|