TVA Colbert

Location – Tuscumbia, Alabama

An intense schedule was the key to this project. Four days after proposals were due, Richard Goettle, Inc. mobilized to the site to install 36 each 26” diameter x 25’ average length drilled shafts. The shafts were socketed into massive limestone. In addition to the drilled shafts, 24 each 40 kip capacity hold-down rock anchors were installed. The project was completed in 15 calendar days.