Project Facts

  • Compressor - 172 micropiles (72 plumb and 100 battered)

  • Plant 3 Mat - 265 micropiles (all plumb)

  • 2 tension/compression tests - one under each structure

Scope

  • Furnish and install 437 micropiles at two sites at the Compressor and Plant 3 Mat

  • Tension/compression tests