CEG WHITE RIVER CCS PHASE 2

(CITIZENS ENERGY GROUP)

Indianapolis, Indiana

Project Facts

  • 1 - 11'-0" dia. x 210 LF drop shafts

  • 1 - 13'-6" dia.  x 210 LF ventilation shafts

  • 220 LF of overburden drilling - fully cased

  • 220 LF of rock drilling

Scope

  • Installation of a drop shaft and ventilation shaft for a combined sewer overflow

  • Removal of overburden material using a crane mounted drill and slurry

  • Removal of rock using a reverse circulation drill