MARKWEST SLUG CATCHER WALL

West Union, West Virginia

Value: $2.1 Million

Project Facts

  • Value engineered design - build (soldier pile wall)

  • 75 pre-drilled soldier piles

  • 115 DCP tie-back anchors

  • 25,000 SF of precast concrete lagging panels

  • 56' maximum wall height

Scope

  • Install 718 LF of permanent rock and soil retention system consisting of soldier piles, precast concret panels, and tie-back anchors

  • The wall originally designed as a soil nail wall