NIPPERT STADIUM RENOVATIONS
(UNIVERSITY OF CINCINNATI)
Cincinnati, Ohio
Project Facts
-
Installed a temporary earth retention system
-
Installed caissons
-
12 week schedule - worked double shifts to meet schedule
Scope
-
48ea. - 30" to 78" dia. Caissons x 30'
-
10 of the caissons were hand dug
-
1,600 SF of temporary earth retention
-
33ea. - tieback anchors x 60' long with 20' rock sockets