PANAMA CANAL

(PANAMA CANAL AUTHORITY)

Republic of Panama

Project Facts

  • 17,000 tons PS-31 sheets

  • 230,000 cubic meters of cell fill

  • 1,400 tons PZC-26 sheets

  • 221,000 cubic meters dredging

Scope

  • Design-Build project

  • Installed 24' - 72' dia. cells

  • Installed 34' - 58' dia. cells

  • Construct 1,500 LF of bulkhead retaining wall

  • Completed to project schedule of 38 weeks