PROJECT PROFILE
Binghamton - Johnson City WWTF
Binghamton, NY
Project completed for:
City of Binghamton
Project Facts
- 142 Secant Piles 5' Dia., 20' - 40' in length
- 17 Caissons at 30" Dia., 35' - 40' in length
- 235 tons re-inforcing steel
- Started March 2016, est. completion July 2016
Scope
- Installing secant piles at 5' Dia. along with 17 Caissons at 30" Dia. in Vestal, New York for the Binghamton Sewage Treatment Plant
- Equiptment used on site: Goettle's BG 40 and a BG39 alongside a Maxim 218 Link Belt Crawler Crane