PROJECT PROFILE
Duke Energy Office Building
Bedford, IN
Project completed for:
Duke Energy
Project Facts
- 12, 7" diameter micropiles
- Average length - 40'
- 3 located inside existing building
- Entrance to existing building 3.5'
Scope
- Limited headroom installation of 7" micropiles at 45' long
- 3 were installed with 12' headroom using a Klemm 701 drill