PROJECT PROFILE

Nanshan Casting Pit

Lafayette, IN

Project completed for:

Nanshan America

Project Facts

  • 96 Ea. 18" Dia secant piles 52' approx. length, total drillinng - 4992 LF under limited headroom
  • Soldier pile wood lagging temporary earth retention system for the first 10 feet of excavation totaling 880 Sq. Ft.
  • Installation of 4576 Sq. of tangent / secant wall under limited headroom
  • Installation of 42" casing for drop shaft 60' in depth

Scope

  • Installation of a drop shaft 55' deep x 22' square inside an existing building with limited headroom to create a Casting Pit for Nanshan America
  • Utilizing temporary earth retention systems, permanent earth retention systems, struts & walers, water extraction systems, secant piles, and the main drilled drop shaft in the center of the excavated pit in existing Nanshan America building