Project Facts

  • 18 ea drilled piers, 30" - 42" diameter, 13' - 24' lengths
  • Installed using Watson EDT-7 drill rig, Watson 2500 drill rig, 210 ton truck crane, 65 ton RT crane, and Skid Steer

Scope

  • Installed drilled pier foundations for school addition. A portion of the drilled piers were installed on an elevated deck that required the drill rig to be picked and placed by crane
  • 512 man hours