SASOL CHEMICAL
Lake Charles, Louisiana
Project Facts
-
Sheet piles at an average of 40'
-
Work started in October 2015
-
Projected completion: August 2016
-
Man hours to date: 20,654
-
Estimated man hours at completion:37,500
Scope
-
Installation and extraction of 40' sheet piles by three crews using Linkbelt 218 HSL's x 3 with 44-50 ICE vibratory hammers
Photos provided by Cajun.