SUMMIT COUNTRY DAY EXPANSION

Cincinnati, Ohio

Project Facts

  • 18 ea drilled piers, 30" - 42" diameter, 13' - 24' lengths

  • Installed using Watson EDT-7 drill rig, Watson 2500 drill rig, 210 ton truck crane, 65 ton RT crane, and Skid Steer

Scope

  • Installed drilled pier foundations for school addition. A portion of the drilled piers were installed on an elevated deck that required the drill rig to be picked and placed by crane

  • 512 man hours

Time Schedule

Critical Schedule - work was to be performed during Christmas break. Start Friday, 12/19/14 and finished Friday, 1/2/15 - on schedule.